Elementary Construction Weekly Update

5.22.2020 Here is the weekly elementary construction update from Garmann/Miiler. Progress this week included Electrical, Mechanical and Plumbing in wall rough where needed • Floor prep for concrete pours continues and concrete pours taken place • Doorframe installation. 